Dia. 900mm Pipeline laying work

Yashwant Gaurav Road Crossing

Vasant Nagari ESR

Sahakar Nagar ESR
LEADING MAIN PIPE LINE WORK AT VASAI EAST AREA


Tamtalav ESR


Works under the AMRUT Scheme
Total Water Tanks in the Scheme – 18
Completed Water Tanks – 5 as follows
1. Moregaon
2. Sahakarnagar
3. Vasant Nagari
4. Madhuban
5. Tamtalav
Water Tanks to be Completed by December 2021 – 3 as follows
1. Naringi Picnic Park
2. Sopara Gaon
3. Gokhivere Survey No. 258
It is planned to complete 10 water tanks by March 2022.
1. Viva College
2. Yashwant Gaurav
3. Jangid
4. Divekar
5. Gokul Complex
6. Dattani
7. Waliv Industry
8. Kargil Nagar
9. EverShine
Separate tender proceedings have been carried out for these water tanks.
Total Length of Water Pipelines – 284 km
Length of Water Pipelines Laid So Far – 238 km
Length of Remaining Water Pipelines to be Laid – 46 km
The work is proposed to be completed by March 2022.
Total expenditure incurred on the scheme so far is Rs. 98.67 crore.
Physical Progress – 70%