वसई विरार शहर महानगरपालिकेमध्ये आपले स्वागत आहे
  • Amrut Mission

    Picture1

    Dia. 900mm Pipeline laying work

    Picture2

    Yashwant Gaurav Road Crossing

    Picture5

    Vasant Nagari ESR

    Picture6

    Sahakar Nagar ESR

    LEADING MAIN PIPE LINE WORK AT VASAI EAST AREA

    Picture3
    Picture4

    Tamtalav ESR

    Picture7
    Picture8

    Works under the AMRUT Scheme
    Total Water Tanks in the Scheme – 18
    Completed Water Tanks – 5 as follows
    1. Moregaon
    2. Sahakarnagar
    3. Vasant Nagari
    4. Madhuban
    5. Tamtalav
    Water Tanks to be Completed by December 2021 – 3 as follows
    1. Naringi Picnic Park
    2. Sopara Gaon
    3. Gokhivere Survey No. 258
    It is planned to complete 10 water tanks by March 2022.
    1. Viva College
    2. Yashwant Gaurav
    3. Jangid
    4. Divekar
    5. Gokul Complex
    6. Dattani
    7. Waliv Industry
    8. Kargil Nagar
    9. EverShine
    Separate tender proceedings have been carried out for these water tanks.
    Total Length of Water Pipelines – 284 km
    Length of Water Pipelines Laid So Far – 238 km
    Length of Remaining Water Pipelines to be Laid – 46 km
    The work is proposed to be completed by March 2022.
    Total expenditure incurred on the scheme so far is Rs. 98.67 crore.
    Physical Progress – 70%